We are replacing (6) 15kv cables between EM2-01 - EM2-04, installing splices, and terminations. Then having the cables tested before final inspection and reenergization. [10-30-26 D Rankin - Waved review, replacement of failed 15kV cable and 5 others] · Electrical
We are replacing (6) 15kv cables between EM2-01 - EM2-04, installing splices, and terminations. Then having the cables tested before final inspection and reenergization. [10-30-26 D Rankin - Waved review, replacement of failed 15kV cable and 5 others] · Electrical