Temporary Battery Energy Storage System (BESS) [7/22/2023 BGO - Approved Plan Set]
Ed Sheeran Concert - Saturday, August 1, 2026
The temporary BESS to be utilized for this event will have a total energy storage capacity of 1,680 kWh.
The system consists of (2) 53-foot flatbed trailers, configured as follows:
Trailer 1: (3) inverters and (6) battery units
Trailer 2: (2) inverters and (4) battery units
The BESS charging system will be supplied by (1) 400A, 480V temporary power feed · Electrical
No product keyword matched · Seattle electrical permits
Adding 2 VOM displays on the south end of stadium on Main Level. Controlled from an existing controller with an added contactor and 20a circuit.
Content is displayed via CAT6 cabling (2) per display. · Electrical
No product keyword matched · Seattle electrical permits
Addition of (2) 20A 120V circuits for lighting & receptacles
(1) 20A 240V circuit for deck heater
Rough-in for (9) can lights, (2) LED linear lights, (1) step light & (2) speaker locations · Electrical
No product keyword matched · Seattle electrical permits