Protection and Mechanical Methods · EQUIPMENT USE: PLACEMENT OF THE KNUCKLE BOOM TRUCK TO ASSIST CRASH DECK INSTALLATION. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
No product keyword matched · NYC DOB building permits
Boiler Equipment · SSCP SOUTH SIDE CHILLER PLANT. DEMOLITION OF GENERATORS ON P-WING ROOF AND DEMOLITION OF EXISTING FUEL STORAGE SYSTEMS SERVING GENERATORS. NEW FUEL STORAGE PUMPING SYSTEMS LOCATED IN THE EXISTING TO REMAIN BASEMENT/GROUND FLOOR LEVEL SERVING NEW GENERATOR
No product keyword matched · NYC DOB building permits
Mechanical Systems · SSCP. South Side Chiller Plant. DEMO AND REPLACE EXIST. COOLING TOWER ON P-WING ROOF. DECOMISSIONING OF EXIST. SATELITE CHILLER PLANTS IN K-WING AND U-WING. ADDITION OF 2 NEW CHILLERS IN THE T-WING FOOTPRINT. CENTRALIZATION OF THE CHILLED WATER SYSTEM.
No product keyword matched · NYC DOB building permits
Sidewalk Shed · INSTALLATION OF A HEAVY DUTY SIDEWALK SHED AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE OF 2022.
No product keyword matched · NYC DOB building permits
General Construction · SSCP South side Chiller Plant. THIS PROJECT WILL REPLACE EXISTING EQUIPMENT AND PIPING INCLUDING COOLING TOWERS, EMERGENCY GENERATORS, AND SUPPORT EQUIPMENT ON THE ROOF OF WING P. THE PROJECT WILL ALSO INSTALL NEW CHILLERS AND SUPPORT EQUIPMENT IN THE BAS
No product keyword matched · NYC DOB building permits
Protection and Mechanical Methods · Installation of temporary crash deck during the Met Tang Wing Addition (filed separately under # M01289549) per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
No product keyword matched · NYC DOB building permits
Protection and Mechanical Methods · Installation of engineered enclosure system for use during partial demolition, filed separately under M01289549-I1.